Article VIII

What is Article VIII?

Since filing our 94-c application in August 2021, the regulatory permitting process for large-scale renewable projects has been moved over to the Department of Public Service and is now governed by Article VIII – Siting of Renewable Energy and Electric Transmission. These changes have no major effect on the South Ripley Solar Project. The former 94-c regulations have been transferred and continue in full force under Article VIII, and ORES still oversees the permitting process for major renewable energy facilities. For a more detailed explanation, please see below.

Effective April 20, 2024, the Renewable Action through Project Interconnection and Development (RAPID) Act (L 2024, ch 58, part O) repealed Executive Law § 94-c, repealed the current Public Service Law article VIII, and enacted a new Public Service Law article VIII entitled “Siting of Renewable Energy and Electric Transmission” (Article VIII). The RAPID Act also transferred the Office of Renewable Energy Siting (ORES) from the Department of State to the Department of Public Service, continuing all existing functions, powers, duties, and obligations related to major renewable energy projects as well as major electric transmission line siting.

With respect to ORES’s regulations at 19 NYCRR part 900, the RAPID Act transfers part 900 to 16 NYCRR chapter XI and continues part 900 in full force and effect subject to conforming changes, such as the substitution of numbering, names, titles, citations, and other non-substantive changes to be filed with the Secretary of State (see RAPID Act §7). The conforming changes were filed with the Secretary of State as a new Part 1100 of Title 16 of the NYCRR and became effective July 17, 2024. Article VIII and the former 19 NYCRR Part 900 (Section 94-c) provide for the State’s consolidated review and permitting process for major renewable energy facilities (25 megawatts or larger).

Article VIII places the review and permitting of such facilities into a single forum, the Office of Renewable Energy and Transmission Siting (ORES). ORES has the authority to issue a single permit for the construction of major renewable energy facilities from both a state and local law perspective. ORES takes into consideration local laws, public health and safety, environmental.

Office of Renewable Energy Siting (ORES)

Article VIII places the review and permitting of such facilities into a single forum, the Office of Renewable Energy and Transmission Siting (ORES). ORES has the authority to issue a single permit for the construction of major renewable energy facilities from both a state and local law perspective. ORES takes into consideration local laws, public health and safety, environmental, social and economic factors pertinent in deciding to permit such facilities. ORES has also been given new functions, powers, duties, and obligations related to major electric transmission siting.

94-c Permitting Process

  • Community and Agency Engagement: The Article VII process prioritizes early engagement with local municipalities, members of the local communities, state agencies and local municipalities, and encourages input to address any concerns from the public before continuing to allow projects to move forward.
  • Environmental Considerations: Projects must be designed to avoid or minimize, to the greatest extent practicable, reflecting New York State’s commitment to environmental protection.
  • Timeline: Article VIII requires that the final decision on a project’s permit be made within one year of the application being completed.
    • Once the application is submitted, ORES reviews and issues a Deficiency Notice, which means the applicant must submit additional information where specified. Once ORES deems the application complete, the one-year clock to issue a final decision begins.
  • Local Law Compliance: Projects are required to comply with substantive provisions of applicable local laws and regulations. ORES can elect not to apply a local law that is unreasonably burdensome in view of CLCPA targets and environmental benefits of the project.
  • Prior to submitting a permit application, renewable energy projects are required to consult with the host municipalities and communities in which the proposed project will be located.
  • ORES also requires that state agencies are consulted and subsequently review and approve decisions involving wetland and stream delineations, threatened and endangered species, and archeological and cultural resources, if appropriate. Agency consultations should take place at the earliest point possible in the applicant’s process.
  • Following consultations with impacted agencies, Article VIII applicants must hold at least one meeting for community members. Notice of the meeting should be provided to community members no sooner than 21 days before the meeting takes place, and no later than 14 days before the meeting takes place. Included in a Article VIII application are copies of meeting transcripts, materials, and discussions. Notice of intent to file an application should be published by the applicant at least 60 days before the application is filed.
  • Municipalities are notified upon ORES issuance of draft permit conditions and are required to provide feedback on the draft permit conditions and compliance with local laws. In addition, there is a 60-day public comment period following the publishing of the draft permit.
  • Outside of the Article VIII public comment period and requirements, South Ripley Solar is committed to continually engaging with the community and considering input. Project representatives have attended nearly every Ripley Town Board meeting and Planning Board meeting since March 5, 2019, to provide project updates and be available to answer questions. Through the South Ripley Solar Project Facebook page, project stakeholders can find accurate, up-to-date project information, updates, and contact information. In addition, the project website has project information, frequently asked questions, and contact information, as well as a form through which comments can be submitted.

Exhibits required as part of an Article VIII Application include:

  • General Requirements
  • Overview and Public Involvement
  • Location of Facilities and Surrounding Land Use
  • Real Property
  • Design Drawings
  • Public Health, Safety and Security
  • Noise and Vibration
  • Visual Impacts
  • Cultural Resources
  • Geology, Seismology, and Soils
  • Terrestrial Ecology
  • NYS Threatened and Endangered Species
  • Water Resources and Aquatic Ecology
  • Wetlands
  • Agricultural Resources
  • Effect on Transportation
  • Consistency with Energy Planning Objectives
  • Socioeconomic Effects
  • Environmental Justice
  • Effect on Communications
  • Electric System Effects and Interconnection
  • Electric and Magnetic Fields
  • Site Restoration and Decommissioning
  • Local Laws and Other Ordinances
  • Other Permits and Approvals

Once the project is has received its final Siting Permit, there is a three-part compliance phase:

  • Pre-Construction Compliance Filings – filing of engineering and design documents, permits, and approvals prior to construction
  • On-Site Compliance – on-site inspections by state agency personnel after construction begins to ensure the project is complying with the Certificate
  • Long-Term Compliance – on-site inspections regarding the operation of the facility over its lifetime

 

Where is South Ripley in the permitting process?

8/10/2021 – Applied for permit.

4/22/2022 – Notice of Complete Application issued by ORES.

4/21/2023 – Final siting permit issued.

Since April 2023, have continued to advance engineering design and working on Pre-Construction Compliance Filing package.

Local Agency Account Funding

Intervenor funding is money that Applicants (i.e., Repsol Renewables) make available to qualified, locally affected parties and municipalities to offset certain expenses they incur in participating in the state permitting process. These funds are meant to encourage early and effective public involvement in project development and permitting.

How to request party status for an Article VIII proceeding

In order to formally file papers related to issues of fact and have them considered as part of the evidentiary record, you must be granted full party or amicus status pursuant to Section 1100-8.4 of the Article VIII regulations. The period for filing a petition for party status shall be at least sixty (60) days from the Office of Hearing’s issuance of notice of the public comment hearing.  Nonparties who wish to have their comments recorded are permitted to submit oral or written comments during the public comment portion of the proceedings, or as otherwise provided by the ALJ. Such public statements will not constitute evidence in the adjudicatory hearing but may be used by the ALJ as a basis for further inquiries.

To request full party or amicus status, an interested party should file a written petition and complete one of the following two options:

For full party status, interested parties should file a petition that includes:

For amicus party status, interested parties should file a petition that includes:

Public Documents and Information

Stakeholder involvement and consultation are part of an ongoing, evolving process throughout all phases of the Article VIII review process. Repsol Renewables’ goal is to provide information to stakeholders, understand stakeholder interests, identify any additional stakeholders potentially affected by the South Ripley Solar Project, solicit information from stakeholders during public outreach events and generally foster public participation in the Article VII review process. Repsol Renewables filed its Transfer Application to ORES to transfer to the Article VIII permitting process, and a new matter number and case docket has been created on DMM.

You may access the Application electronically through the links above and on the New York State Department of Public Service’s Document Matter Manager (DMM) system, or you may access hard copies of the Application at one of the following locations:

Ripley Town Clerk’s Office

14 North State Street
Ripley, NY 14775

Monday, Tuesday, Thursday, and Friday 9:00 AM-12:00 PM, and 1:15 PM-4:00 PM, Saturday 9:00 AM-12:00 PM

Ripley Library

64 Main Street
Ripley, New York 14775

Monday, Wednesday, and Friday 10:00 AM-5:00 PM, Tuesday and Thursday 10:00 AM-7:30 PM, and Saturday 9:00 AM-2:00 PM

Office of Renewable Energy Siting

Empire State Plaza
240 State Street
P-1 South, J Dock
Albany, NY 12242

During normal business hours

To view the South Ripley Solar Project’s Article VIII application, click here.

Please note: as additional documents are filed, this section will be updated.

Public Comment

Any party wishing to remain a party under the Article VIII process is encouraged to review the Article VIII regulations and to contact the ORES office with any questions at: general@ores.ny.gov.

To stay up to date about the South Ripley Solar Project, please join our stakeholder notification list by filling out the contact form here. You can also call us at (800) 338-8905 or email info@southripleysolar.com.

Connectgen’s South Ripley Solar Project Receives Approval From the New York State Office Of Renewable Energy Siting

ConnectGen announced today that its proposed South Ripley Solar Project has received a final siting permit from the New York State Office of Renewable Energy Siting (ORES). Based on a comprehensive review of the record, ORES found that the Project complies with Executive Law 94-c and avoids, minimizes, or mitigates, to the maximum extent practicable, potential significant adverse environmental impacts to the surrounding area.

This website uses cookies to improve your experience on our site. By using clicking ‘accept’ you consent to the use of cookies. Learn more.